BUDGET: Between 5 crore INR and 9.99 crore INR (More than USD672,000 but less than USD1.35 million)



Project Overview

We have laid a futuristic plan and ordered the equipment. We laid approx. 95000 meters CAT6A, 2000 meters optical fibre, 8000 meters RG6 cable. 6000 meters of speaker cable and various patch cords for 5000 Nodes for voice and data have been installed at workstations/end points. We have installed various equipment, like network Active and Passive with CAT6A, Copper Media and single-mode OFC with 10G Network. We have also provided IP, digital, and analogue telephonic facilities for 504 users. 62 Norden High Resolution CCTV surveillance system with 45 days recording. 197 IP PA systems with 6-zone digital Paging and announcement system.

We have installed 74 numbers of Brio IFP Panels/displays of various sizes like 55”, 65”, 75”, 98” and 110” with 21.5” Retractable and Room Schedulers in all the Meeting rooms, Conference Room and Board Room.

We have installed 70 Televic Chairman-Delegate Units with controlling devices for the main conference Hall and Board Room.

We have installed 28 Aver All-in-One Bars for Video Conferencing in the various officers’ rooms.


What did the client want to achieve?

The client wanted to achieve state-of-the-art Audio Visual and Information Technology (AV & IT) equipment across all three floors of the RVNL WTC facility, featuring the latest generation of advanced and upgraded technology solutions. The deployment enhances collaboration, communication, presentation capabilities, and operational efficiency throughout the premises.


Scope of work your company was involved in

Our company was involved in Audio Visual and Information Technology (AV & IT) works as per the scheduled items in the tender.


What key challenges were faced?

The challenges were civil works, such as furniture and furnishing, as per the approved drawings.


How were those challenges resolved?

Many times, follow-up with a full-day engagement with project managers.


How has your work helped the client?

We completed the work within the time frame, and they appreciated the excellent work as per the schedule.


What are you most proud of about the project?

We are proud of our entire team, the customer and the PMC team.


VIDEO link of the project space: Not available.